Infrastructure – Hydraulic Jacking, Monitoring Equipment and Temporary Propping

Stockley Junction Viaduct Flyover

Network Rail / Crossrail

Description of Project

Stockley Flyover is a £90 million Crossrail project that is being delivered by Network Rail. The objective is to construct a new flyover to facilitate Crossrail and Heathrow Express services between London and Heathrow Airport, whilst allowing trains to Reading and beyond to pass through the junction unhindered.

The works consist of constructing a viaduct structure of numerous support piers of approximately 1.5 km distance.

At each pier location a temporary propping support system was installed to support the newly installed RC beams, which were required to be preloaded and assist with bearing installation.

Professional Services

Over 100 number 100 tonne capacity hydraulic jacks, were supplied to the contractor with all the applicable hydraulic accessories (ie. manifolds, hoses and hydra-packs to control jacks individually, and/or as pairs and sets.

This synchronised lifting system allowed all jacks to be lifted and monitored by real-time instruments for accurately levelling each reinforced concrete beam as per the Consultant Engineers’ specifications. In addition, the jacks were used part of the bridge sliding operation.

Each bridge deck have a number of hydraulic jacks interlinked to control the alignment of the bridge bearings and support the pier decks until the super-structures had achieved the recommended strength

"Over 100 hydraulic jacks were supplied as part of a com-puterised control system to accommodate beam alignment and load transfer into newly installed bridge bearings"

Such projects require carefully planning and project management due to all the works being completed within tight time schedules. Hydra Capsule were able to provide a 24/7 back-up service and team for assistance throughout the project. Ensuring all programmes were achieved.

The monitoring equipment provided by Hydra Capsule were manufactured in-house and provided movement sensors accurate to +/- 0.10mm and load / pressure monitoring to +/- 1 kNs.

Project Features

  • Hydraulic Jacking System
  • Design of Synchronised Control System
  • Monitoring and Pressurising Equipment
  • Hydraulic Locking Collar Jacks to suit Jacking Units
  • Training and Consultancy with Temporary Propping System

Duration of Works

January 2014 to September 2014


Connect With Us



Find Us


Address

Hydra-Capsule Limited
Hydra House - Bishops Frome
Worcestershire
WR6 5BP

© Copyright 2024 Hydra-Capsule Ltd