Civil Engineering and Infrastructure – Bearing Replacement and Bridge Jacking

M27 Park Gate Bridges, Fareham

Highway Agency

Description of Project

Hydra Capsule have recently completed a major preloading and bearing replacement on the M27, junction 9 for the Highway Agency. The works consisted 84 number 50 tonnes capacity flat jacks, elastomeric / fixed and uni-guided bearings with additional temporary and permanent structural steel support works.

Both bridges consist of a central concrete pier with 19 nr. reinforced concrete beams (38 nr. in total) , which spanned 22 metres per side of the M27 motorway. A total of 78 nr. beams were sat onto existing bearings and concrete piers which were bearing badly corroded and in need for reconstruction due to structural fatigue concerns

Professional Services

Due to the restricted working space, 50 tonnes flat jacks were supplied to pre-load the newly installed elastomeric bearings, all carried out by Hydra Capsule. The concrete bridge deck was synchronously pre-loaded in stages, and lifted only by +2.00mm, controlled by digitally electronic displacements gauges (LVDTs) and a pumping system.

To be adjustment and pre-loaded from a central control point, working within a tolerance of 0.25mm differential between adjacent beams. Hydra Capsule were commissioned to offer a full bearing design proposal for the existing 76 nr. beams and additional 8 nr. fixed and uni-guided bearings for the bridge abutment and central concrete piers. This allowed reinstallment of the central bridge piers (East and West) while the flat jacks worked under “live” loads throughout the 9 month project.

“Hydra Capsule were employed to pre –load and load transfuse all replacement bearings under live traffic conditions and accuracy to 0.25mm”.

Once the works had been completed. Hydra Capsule transfused the temporary work loads into the flat jacks, maintaining the 0.25mm tolerance, ensuring the total loads to each bearing(s) had been distributed equally. Once achieved, all the flat jacks were individually grout transfused, maintaining a gradual load and movement tolerance, until the jacks were fully filled with high-strength cementitious grout.

Further work that Hydra Capsule complete at the Park Gate project, included additional temporary steelwork supports at the central piers and abutment parapets. Due to the nature of the bridge and temporary propping system, Hydra Capsule were required to install lateral and longitudinal supports to reduce the risk of the bridge structure twisting at the abutment locations and reduce any potential cantilever loading in the central supports, whilst hydro-demolition was completed.

Project Features

  • Hydraulic Jacking System (+/- 0.25mm accuracy)
  • Transfusion Flat Jacks (manufactured and testing in-house)
  • Temporary Support System – Bespoke steel fabrication
  • Manufacturing of Permanent Bridge Support Steelwork
  • Bearing Replacement – Supply & Fix (Elastomeric, Fixed and Guided)
  • Pre-stressing and Post-tensioning

Duration of Works

March 2013 to December 2013


Connect With Us



Find Us


Address

Hydra-Capsule Limited
Hydra House - Bishops Frome
Worcestershire
WR6 5BP

© Copyright 2024 Hydra-Capsule Ltd