Construction – House Lifting – Synchronised Jacking System & Temporary Propping

Wraysbury, Staines

Private Individual

Description of Project

Recent flooding last winter in 2013 caused the heaviest rainfall in almost 250 years. Around 1,000 homes were badly damaged in Somerset and along the Thames Valley. Numerous methods are being implicated by the Environment Agency to prevent flooding happening again.

However, one gentleman decided to approach Hydra Capsule with a challenging project. To raise his house +1.50 metres. Hydra Capsule worked with the consultant engineers to accommodate a design a system to lift accurately to 1.00mm, which was successfully completed over 5 days.

Further details of report are on https://news.sky.com/story/house-lifted-15m-to-avoid-more-flood-misery-10392106

Professional Services

28 number hydraulic jacks, with 50 tonnes capacity and had a 300mm maximum stroke. Were inter-linked to a computerised central –control system, which electronically controlled all the hydraulic jacks synchronously and independently to suit the requirement of the levelling and lifting of the house.

This synchronised lifting system allowed all jacks to be lifted together in 280mm stages. Each jacking location were digitally monitoring by our electronic instrumentation (ie. draw-wire potentiometer and pressure sensors), allowing Hydra Cap-sule to have complete control throughout the operation(s). The total lift of the slabs were +1.55 metres in height.

"Over a period of only 5 days, the house was lifted 1.5 metres accurately to +/- 1.00mm across all jacking locations. One of the largest domestic lifts in Europe"

The complete jacking operation was completed all with-in 5 working days, as a result of using a jack-and-pack method. This allowed jacks to be paired together and lifted alternatively for speed, control and safety.

In addition, a steel girder needling framework arrangement was installed throughout the perimeter of the house and once the cylinders had been pre-load the wall was diamond-cut to allow the building to be free of any constraints and lift freely.

Sean Davies, senior project engineer, of Hydra Capsule said: "We’re used to doing larger bridges and structures, however, this lift was very technical and challenging due to the risks. However, the synchronised jacking system we have designed in-house allows us to more confident to complete projects like these"

Project Features

  • House Lifting – Jacking Buildings out of Flood Risk areas
  • Hydraulic Synchronised Control System
  • Temporary Propping Support System
  • Temporary Propping Full Design Service
  • Supply and Fix Package
  • Hydraulic Locking Collar Jacks

Duration of Works

September 2014


Connect With Us



Find Us


Address

Hydra-Capsule Limited
Hydra House - Bishops Frome
Worcestershire
WR6 5BP

© Copyright 2024 Hydra-Capsule Ltd